Unforseen Design Problems of the 747-400 Electrical Power Generation Systemby Carl Tenning |
|
| Note: This article is of historical interest only, since the problems described here have long since been fixed. But it does illustrate some of the unforseen circumstances faced by the designer. | |
|
The electrical power generation system for the 747-400 was a new design from
previous 747 variants. Whereas the previous 747 Models were all designed to include a Flight Engineers
station on the flight deck, the 747-400 was a two-crew flight deck. As such, the electrical power
system control panel was designed into the pilots overhead panel instead of on the Flight Engineers
side panel. By this time, Boeing had considerable experience in the designing an electrical power
system for a two-crew flight deck. Previous two-crew designs were the 737, 757 and 767. The 747-400
had a number of features differing from the previous 747 variants, designed to simplify system
operation and improve electrical power quality, reliability, and maintainability. These new features
included:
|
|
|
With the engines running, electrical power is supplied by four Integrated
Drive Generators, one on each engine and rated at 90 kVA each (Figure 1). The generators operate
in electrical parallel, i. e. not isolated as in most two-engine airplane systems. A generator
circuit breaker (GCB) connects the output of each generator to its respective bus. The main buses
are connected to a tie bus (sometimes referred to as the synchronizing bus, or sync bus for short)
through the bus tie breakers (BTB). The tie bus is split into two halves which are connected
together by the split system breaker (SSB). With all IDG's operating, the four GCB's, four BTB's
and the SSB are all closed, i.e. connected. For ground operations there are two direct drive APU
generators and two external power receptacles for powering the airplane. Power from each APU
generator is connected it its respective side of the sync bus through its APB contactor.
Likewise, power from each external power receptacle is connected it its respective sync bus
by its XP contactor (XPC). Each APU generator is rated at 90 kVA and each external power receptacle
is rated at 90 kVA.
|
Figure 1, Main AC System |
|
DC power is supplied by four Transformer Rectifier Units (TRU), one to each main
DC bus (Figure 2).
The four DC buses are operated in parallel by four DC Isolation Relays (DCIR). The DCIR's are normally
closed, (conducting), but open for system isolation during autoland. The Captain's and First Officer's
instrument buses are powered from the main AC buses through the Instrument Bus Voltage Sensing Units
(IBVSU). These automatically transfer the instrument bus power to AC Bus-1 in the event that the normal
source fails, which is AC Bus-3 for the Captain's instrument bus and AC Bus-2 for the First Officer's
instrument bus.
|
Figure 2, DC System |
|
The pilots control module for the electrical power generation system is in the
pilots overhead panel (P5, Figure 3). There are four drive disconnect switches at the bottom of the
module. These are guarded switches. Lifting the guard and pressing the switch will cause the IDG shaft
to mechanically disconnect from the engine gearbox. This would only be done in the event of an
overheated IDG or low IDG oil pressure. Once disconnected, the IDG cannot be reconnected in flight.
|
Figure 3, Control Panel |
|
Above the disconnect switches are generator control switches. These are mechanically
latching switches, latched in to keep the generator on and latched out for shutting a generator off.
These switches remain in the ON (or in) position for all normal operations. Leaving these switches in
the ON position permits the generators to automatically connect to the buses when the engines start.
Above the generator control switches are the bus tie control switches. These switches control the operation of the BTB's and have the same mechanical latching action as the generator control switches. With the switch latches in, the BTB operation is automatic. With the switch latched out, the respective BTB and DCIR is opened (isolated). Above the bus tie control switches are the external power and APU generator
control switches. These are spring back momentary action switches. Momentarily pressing the switch
when the power source is available commands the source to connect to the sync bus. Conversely, if
the switch is pressed when the source is already connected it commands the source to disconnect.
There are two external power control switches and they operate in the same manner as the APU generator
control switches. External power is obtained from two
|
receptacles on the lower forward fuselage.
The aircraft electrical system does not parallel the two external power sources or the two APU
generators. If only a single external power receptacle is connected, then selecting that external
power source onto an unpowered airplane will power both sides of the sync bus by automatically
closing the split system breaker (SSB). However, if both external power sources are selected,
the SSB will open so that each external power source will only connect to its respective side of
the sync bus. The same is true for the APU generators.
On the aft overhead is the electrical system maintenance panel (Figure 4). Each of these switches are guarded momentary action toggle switches. These switches are intended for maintenance use only and as such are out of the pilots normal reach. The four IDG field switches permit energizing the generator field when the generator control switch is off. These switches have no effect when the generator control switches are on. The two APU generator field switches permit energizing and de-energizing the APU generator fields. Indicators illuminate when the respective generator fields are off. The Split System Breaker switch will alternately open and close the SSB. This switch is inoperative in flight (AIR Mode). The SSB indicator illuminates when the SSB is open. |
Figure 4, Maintenance Panel |
|
|
Parameters of the electrical power generation system can be displayed on the
EICAS maintenance page (Figure 5). Voltage, frequency and load are displayed as well as IDG oil
temperatures. A synoptic page displays the configuration of the AC electrical system by showing green
for the parts of the system that are energized and amber for the parts that are not energized.
|
Figure 5, EICAS Maintenance Page |
|
The brains of the 747-400 electrical power generation system (EPGS) are
contained in the four Generator Control Units (GCU), originally P/N 60B40162-1 and two Bus
Control Units (BCU) originally P/N 60B40162-2. Each of these units is operated by a microprocessor
which controls system operation, provides fault protection, and performs automatic built-in-test (BIT).
During development testing of this system, a number of special characteristics were found too late to be changed before initial entry into service. Still other characteristics were discovered during early in-service operations. While these characteristics did not affect the safety of operations, they did pose somewhat of a nuisance to the operators. Each item was carefully documented ,analyzed, and tested. Modifications, i.e. corrections, for these characteristics were then |
incorporated into the next release of the GCU and BCU,
60B40162-6 and 60B40162-7 respectively,
which began delivery with new airplanes in October 1989. Approximately 120 separate changes were
incorporated in this revision. While many of these fixes were the result of software changes, some
internal hardware also required changing. Each of the internal circuit boards and wire harnesses was
either modified or replaced. Airplane retrofit was accomplished by Boeing Service Bulletin 747-24-2122.
Here are twenty four examples of special characteristics found during the development and early in-service experience. Twenty of these, and many other characteristics, were corrected by the Service Bulletin and on follow-on deliveries. |
Unplanned Characteristic No. 1: Power-Up Sequence SensitiveBCU-1 is normally powered from the Main Battery Bus and BCU-2 from the APU Battery
Bus. However, each BCU also receives operating power from its respective XP receptacle. If power
is applied to an XP receptacle before turning on the Battery Switch, an "ELEC BCU" fail message is
generated an EICAS because the BCU failed to sense battery power. Also, since one BCU will typically
receive power before the other, the powered BCU seeing no ARINC-429 signal from the other, causes
the autoland function to be locked-out. In addition, the load shedding function does not function
as intended when this happens. Powering up in this manner will display an "ELEC BCU' message on
the EICAS status page, preventing the airplane from being dispatched in this condition. The proper
operating procedure, until the -6 and -7 control units are installed, is to always power up with the
battery switch before connecting the external power cables. In addition it is necessary to wait a
minimum of 20 seconds after turning on the battery switch in order for the BCU's to complete their
self test. The standby power switch must also be OFF during this time to prevent a nuisance "ELEC BCU"
message.
|
Unplanned Characteristic No. 2: Latching of Messages Causes Nuisance IndicationA number of nuisance messages were found to occur due to the built-in-test functions in this system.
A nuisance message is generated when the built-in-test erroneously detects something failed. In the -1 and
-2 control units, all messages are latched, i.e. permanently set until the units are powered down. Thus,
even if a condition was temporarily detected as failed, for example due to an unforeseen sequence of
events during power-up, a permanent message was set. While these erroneous messages are eliminated in
the -6 and -7 control units, the original system has to be completely powered down (including removal
of the ground power plugs) to clear any nuisance messages, In the -6 and -7 version, latching of messages
has been removed in addition to modifying the built-in-test logic. Where latching is truly required,
it will be performed within the Integrated Display System and the Central Maintenance Computer.
|
Unplanned Characteristic No. 3: Anomalous APU Generator Control Switch ResponsePressing the APU generator control switch commands the APU generator to be connected. When applying
the APU generator to the bus, it may be the first source an the bus or it may be transferring from either
the IDGs or from external power. When the APU generator is the first source an the bus, the action takes
place immediately. But when transferring from an IDG, the IDG must first synchronize with the APU generator.
Synchronization by an IDG is fast enough that the delay is normally not noticeable. Power transfers to
external power, however, may take a few seconds while the APU engine changes speed to synchronize with
external power. This time delay is sometimes confusing to the operator. Thinking that the APU did not
respond, the operator may attempt a second or third try at the switch. In the original version, a
second attempt at the switch (before the APU has synchronized with external power) causes the command
to be reversed, further confusing the operator. The reason for this is that the BCU control logic resets
the previous switch command when the switch is pressed again. To further complicate things, there is
a situation where two actuations of the APU Generator Control Switch are required to reset the APU
generator (see Unplanned Characteristic No. 17). In the -7 BCU, the switch latched logic is not reset
until after its initial power transfer is complete (or after 4.5 seconds, if power transfer does not complete).
Thus each new actuation of the switch is sensed in proper relation to its intended command.
|
Unplanned Characteristic No. 4: APU Failure To Synchronize With External PowerTo obtain no-break power transfers between the APU generator and external power,
the APU is speed jogged to obtain momentary synchronization. The power then transfers when the frequency
of the two sources are within 5 Hz and +/-90 degrees phase angle. Speed jogging only occurs when the
frequency difference exceeds 5 Hz. As long as the two frequencies are not exactly the same, phase
alignment within +/- 90 degrees will quickly occur. However, if synchronization (paralleling) does
not occur within 3.5 seconds, the system is designed to perform a 'break," transfer. Synchronization
may not occur quickly enough if both sources are nearly the same frequency. When both frequencies are
within 0.14 Hz of the same frequency, phase alignment can take longer than 3.5 seconds, resulting in
a "break" transfer. This characteristic is modified in the -7 GCU to always command the APU to speed
jog, even when the frequency difference is less than 5 Hz.
Another characteristic of APU speed jogging was found to occur when one external power source was above 400 Hz and the other was below 400 Hz. Assume that the airplane was operating on external power with XP1 at 415 Hz and XP2 at 385 Hz. Selecting the APUl switch would commence the APU speed joqqinq toward 415 Hz. If the APU2 switch were selected before XP1 had a chance to transfer to APU generator #1, then the speed jogging would reverse direction, toward 385 Hz. This would cause a 'break' transfer on the APU generator #1 side. This is revised in the -7 BCU so that the first power transfer will be completed before the direction of speed jogging is reversed. |
Unplanned Characteristic No. 5: System Lockup From Pressing Both External Power Switches Or Both APU Generator Control Switches At The Same TimeAssume that external Power is to be connected to an unpowered airplane.
Depending an the previous state of operation, the SSB can be either open or closed before external
power is applied. If the SSB was already closed, then pressing both external power control switches
at exactly the same time will cause the external power control to lock up, preventing any application
of external power. The same is true of the APU Generator Control Switches. The airplane must be
completely powered down to recover from this condition, i.e. battery switch off and both external
power plugs disconnected. This characteristic is modified in the -7 BCU so that simultaneous switch
operation will not prevent power application.
|
Unplanned Characteristic No. 6: Incorrect External Power and APU Generator Frequency IndicationSystem voltage, frequency and load are displayed on the flight deck maintenance
display. The information that it displays is transmitted to the indication system from the BCU over an
ARINC-429 communication link. The original BCU design transmitted a default frequency of 122 Hz when
the APU generators were not running. Since the frequency for this condition should be indicated as zero,
the -7 BCU has been revised to indicate "FREQ 0" for this condition.
|
Unplanned Characteristic No. 7: Incorrect External Power "AC CONNECTED" and "POWER NOT IN USE" IndicationThe system will not permit external power to be applied to the aircraft buses
unless the power quality is within acceptable limits. However, when external power is plugged into
the airplane, these indicators at the external power receptacle illuminate even if power quality is
outside of these limits. With the -7 BCU installed, these indicators will only illuminate when external
power quality is within limits.
|
Unplanned Characteristic No. 8: Unnecessary Simultaneous "AVAILABLE" and "ON" Indication For External Power and APU Generator PowerWhen external power or APU power is connected to the buses, both the "AVAILABLE"
light and the "ON" light on their respective control switches remain illuminated. This was causing
the face of the switch to be hot to the touch. With the -7 BCU installed, the "AVAILABLE" light is
extinguished whenever the "ON" light is illuminated.
|
Unplanned Characteristic No. 9: Application of a Single Generator To Both Sides Of The Sync Bus In FlightThe system is designed such that a single generator can supply all four main
buses. To do this the split system breaker (SSB) must be closed, which would normally be the case.
However, if for some unforeseen reason the SSB were to open in flight in combination with temporary
loss of all four generators, the SSB will not automatically re-close when a single generator is restored.
Thus the restoration of a single generator, in this case, would power only two main buses. A second
generator must be restored an the opposite side of the sync bus in order to restore power to the
remaining two main buses. Powering at least one generator on each half of the sync bus will close
the SSB in flight. [It should be noted here that this represents a highly improbable failure mode.
While it is intended that the restoration of the first generator will apply power to all four main
buses, even restoring power to only one bus will still power all four DC buses. This is because
there is no split system contactor in the DC Tie Bus and a single TRU can supply all four main DC
buses.] With the -6 and -7 control units installed, the SSB will automatically re-close under this
condition so that a single generator will restore power to all four main buses.
|
Unplanned Characteristic No. 10: SSB Operation For Single Engine Push-back With APU InoperativeWhere airport rules require push-back before engine start, the APU would normally
provide electric power during this time. However, in cases where the APU is inoperative it may be
necessary to push back using one engine to supply electric power. Assuming that the aircraft was
powered from the two external power plugs before starting the engine, the split system breaker (SSB)
would be open. When only one engine is started, it's generator will power only one half of the sync
bus. External power continues to supply the other half of the sync bus. That half of the sync bus
would then become unpowered when external power is disconnected unless the SSB is manually closed
before push-back. This makes it necessary to operate the SSB control switch on the overhead maintenance
panel, which is inconvenient since the pilot cannot reach this switch from his normal position.
The -6/-7 version of the system changes the operation so that the SSB will close automatically when
the first engine generator comes on line.
|
Unplanned Characteristic No. 11: Transferring From Two APU Generators to a Single XP Source or From IDG's to a Single APU or Single XP SourceThe SSB is open when the airplane is powered from the two APU generators.
Transferring to a single XP source (XP1) in this condition transfers the left sync bus to the XP
source, leaving the right sync bus powered from APU generator #2. Subsequent shutdown of APU
generators leaves the SSB open causing the right sync bus to become unpowered. The SSB switch
must be operated to restore power to the right half of the sync bus. The -7 BCU has been modified
to automatically reclose the SSB under this condition, eliminating the need to operate the SSB switch.
When transferring from IDG's to APU or XP with only a single source available, the single source will automatically connect to both halves of the sync bus. But when both APU sources or both XF sources are available, each source will connect only to its respective side of the sync bus. Ordinarily both sources would be selected, thus powering both sides of the sync bus. But consider the case where the "AVAIL" lights are inoperative on one APU generator or one external power source-, unless the operator pressed the switch with the inoperative lights, APU power or XP power would not be applied to that half of the sync bus. That side of the sync bus would then become unpowered when the IDG's were shut down. This was changed in the -6 and -7 units to automatically close the split system breaker (SSB) when the IDG's are shut down under this condition, preventing a dead bus. |
Unplanned Characteristic No. 12. Incorrect Battery Voltage SensingThe BCU's monitor their respective battery voltages for the purpose of displaying
battery voltage on the EICAS Maintenance page. BCU-1 monitors the main battery and BCU-2 monitors
the APU battery. An "ELEC BCU" message was generated if this voltage was below 10 volts or above
30 volts. Since the battery can normally exceed 30 volts during charging, this logic would generate
a nuisance "ELEC BCU" Message. Prior to delivery of the -2 BCU this was corrected by the addition
of zener diodes in the airplane wiring, to prevent the BCU from seeing voltage in excess of 30 volts.
Due to the zener in the system, the battery voltage indication an EICAS cannot read above 30 volts.
This characteristic is changed in the -7 BCU so that the zener diodes are no longer required and true
battery voltage, when it is above 30 volts, can be displayed on EICAS. The message generated when
the battery sense input is below 18 volts is changed to BAT BUS SENSE INPUT FAIL and is displayed on
CMC only.
|
Unplanned Characteristic No. 13: Nuisance "CMC>BCU BUS" Fail Message On CMCA self test of the electrical power generation system can be initiated manually
from Central Maintenance Computer (CMC). The request for a self test is transmitted from the CMC to
the BCU over an ARINC-429 digital data transmission bus. If for some unknown reason the CMC should
fail in such a manner that it repeatedly transmitted a request for test, while it did not affect system
control or protection, it was found to temporarily cause blanking of the electrical system display on
EICAS. To overcome this possibility the 747-400 airplanes had a relay installed in the ARINC-429 line to
disable this input during flight. As a result of the added relay, the BCU detects that this input is
disabled and displays a nuisance `CMC>BCU BUS" message on the CMC. The software in the -7 BCU is
modified such that the relay in the ARINC line will no longer be required. In addition, the CMC nuisance
indication is eliminated by inhibiting this message when the airplane is in the AIR MODE.
|
Unplanned Characteristic No. 14: Load Shed When Jacking AirplaneThe system automatically sheds the utility and galley buses in the air whenever
there are less than two IDG's powering the buses. This affects maintenance when jacking the airplane
because the system would sense AIR MODE and unnecessarily shed the utility and galley buses. This has
been modified in the -7 BCU so that AIR MODE load shed will not occur if the airplane is powered from
external Power. Load shed will still occur if the airplane is being powered from the APU generators.
This is so that an attempt to inadvertently take off using APU generators only (i.e. without the IDG's
powering the buses) would be readily detectable. AIR MODE is detected whenever the weight-on-wheels
sensors are off the ground or engine speed on three or more engines is above approximately 74% N2
(67% N3 for RR engine).
|
Unplanned Characteristic No. 15: Slow Drop Out of XPC Causes Nuisance BTB TrippingThe system has Sustained Unlike Source Protection (SUSP) which will trip the BTB if either the APU generator or external power source remain continuously paralleled with an IDG (i.e. the GCB fails to trip). Slow drop-out of the XPC due to the spike suppression circuit can cause this to occur. The spike suppression circuit in the -7 BCU has been modified to increase XPC drop-out time. The GCU software has also been modified to positively prevent inadvertent SUSP tripping.
|
Unplanned Characteristic No. 16: Nuisance "APU BAT CHARGER FAIL" MessageThis occurred because the input power to the APU battery charger is removed during APU cranking. The BCU erroneously flagged this as a failure of the battery charger. A 1.7 minute time delay for this message has been added to the -7 BCU to Prevent a nuisance indication.
|
Unplanned Characteristic No. 17, Nuisance "AUXILIARY POWER BREAKER/AGCU FAIL" MessageThis message occurred on CMC due to APU engine shutdown without first disconnecting
the APU generator. In this situation the APB is tripped by a command from the APU Generator Control Unit
(AGCU) instead of the BCU. Since the BCU did not issue the command to trip, its logic perceived the
APB or AGCU as failed. In addition, after the APU is restarted, it requires two actuations of the APU
Generator Control Switch to restore power to the APU generator. Both of these characteristics have
been revised in the -7 BCU to eliminate the nuisance indication.
|
Unplanned Characteristic No. 18: Nuisance "IDG LOW OIL PRESSURE" Message On Cold Day Engine StartWith high oil viscosity due to engine cold soak, the oil pressure build-up in
relation to engine speed during starting occurs late in relation to engine speed. This causes Monitor
BIT to erroneously generate the "IDG LOW OIL PRESS" message on the CMC and results in the "ELEC GEN SYS"
message an EICAS Status. This is modified in the -6 GCU to prevent the nuisance indication.
|
Unplanned Characteristic No. 19: Nuisance "ELEC GEN SYS" Message For In-flight Engine ShutdownSlower engine deceleration rates are experienced when an engine is shut down in flight
than when it is shut down while the airplane is stopped. This caused the GCU logic to incorrectly generate
this message on EICAS Status. This has been revised in the -6 6CU to eliminate the nuisance message.
|
Unplanned Characteristic No. 20. Nuisance "ELEC IDG VALVE" MessageThe GCU interprets the IDG air/oil cooler valve as failed if the valve is open
when it has not been commanded open by the GCU. This results in an "ELEC IDG VALVE" message sent to
EICAS and an "IDG COOLER VALVE" message sent to the CMC. The cooler valve, however, can also be opened
by the engine control system (EEC) as well as by low pneumatic pressure. This always results in a
nuisance message on CMC. The EICAS message, however, is inhibited by the EIU when the valve is commanded
open by the EEC and also when engine N2 is less than 88%. A nuisance message can still occur due to low
pneumatic pressure at engine speeds above 88%. The logic for the CMC message was modified in the -6 GCU,
but the logic for the EICAS will not be changed until the next EICAS modification. Since the EICAS message
is latched by the EIU, the nuisance EICAS message may still occur.
A truly failed valve will still be indicated if the valve does not open when commanded to open by the GCU. |
OTHER CHARACTERISTICS
|
|
Unplanned Characteristic No. 21: Nuisance "BAT DISCH APU" MessageThis message occurred when the battery reached full charge and the charger
switched to the float charge made. The battery reaches approximately 32 volts at the end of charging
when the charger switches to 27.5 volts for the float charge mode. At this time the battery is
temporarily at a higher voltage than the charger. This will, cause the battery to discharge for a few
seconds, until the battery voltage matches the charger voltage. If there is more than 7.0 amperes
load on the Hot Battery Bus, the "BAT DISCH APU" message will appear. This temporary message was
inhibited in the Integrated Display System Electronics Interface Unit (EIU) by increasing the time
delay for this message to 60 seconds,
|
Unplanned Characteristic No. 22: Nuisance "ELEC SSB OPEN" MessageEICAS Advisory originally displayed this message whenever the SSB was open.
Since it is normal for the SSB to be open when operating from the APU or external power, this
message was an annoyance. The logic of the EIU was changed to only display the message if the SSB
was open when it should be closed. Fortunately this information was already available from the BCU
via the ARINC-429 serial data link.
|
Unplanned Characteristic No. 23: Load Shed During Taxi-in When Operating On APU GeneratorIf the airplane is taxied with the electrical system powered from only the APU
generators, advancing three or more throttles causes the system to switch to the AIR MODE. This results
in an immediate load shed of all utility buses and galley buses. To prevent this load shedding, the airplane
should remain on IDG electrical power until completing taxi. Load shed is designed to protect the IDG's
from overload by automatically shedding these loads whenever the airplane is in the AIR MODE and there
are less than two IDG's powering the system. AIR MODE is sensed either by the weight on wheels sensors
or whenever three or more engines are above airmode speed (74% N2 for GE engine, 73% N2 for PW engine,
or 67% N3 for RR engine). This feature also alerts the crew if takeoff is attempted with the electrical
system powered from the APU generators.
|
Unplanned Characteristic No. 24: Shock Load On Power Transfer To APUWhen transferring power from XP to APU, the APU speed jogs to synchronize with
the external power frequency. If the external power frequency is low (near 380 Hz), the APU is
decelerating when the power transfer occurs. The shock load application while the APU is decelerating
can cause the APU to go under-speed. This is a characteristic of the APU and its controller. All power
may be lost when this happens, depending on whether one or both APB switches were selected. This is
because XP disconnects immediately after the APB closes. If only one APB switch was selected, then
only half of the sync bus would go dead. Reselecting an APU generator or XP source onto a dead bus
would reestablish power to all buses. With the -7 BCU installed, the SSB would automatically re-close
under this condition, transferring power to the opposite XP and preventing a dead sync bus.
The above condition can also occur when transferring from IDG power to APU generator power. If the second APU generator control switch is pressed before the first APU generator has transferred power, both APU generators may get power applied at the same time, This can be avoided by waiting for the first APU generator to transfer power before selecting the second generator. |
|
|